Sprinkle Road Construction Project Starts Monday. Expect Long Delays!
It starts this coming Monday. Beginning with a week of electrical work, the rebuilding of the Sprinkle Road Bridge and interchange over Interstate 94 (complete with a pair of controversial round-a-bouts) begins Monday, March 23rd.
Here's the schedule put out by MDOT.
Reconstruction of the Sprinkle Road bridge and interchange at I-94 will start Monday, March 16.
What work is taking place now?
- Barrels and barricades are arriving in preparation of closing Sprinkle Road lanes and ramps Monday.
- Utility relocation is underway.
- Tree removal is underway.
What work is taking place in the next week?
- Ramp closures at the I-94 Sprinkle Road interchange.
- The ramps will be removed. Grading will start for the new ramps.
- The construction of the new Sprinkle Rd Bridge will start.
The following closures apply to Sprinkle Road ramps and Cork Street as indicated (weather dependent).
- EB I-94 ramp to NB Sprinkle Road
- EB I-94 ramp to Southbound Sprinkle Road
- WB I-94 ramp to Cork Street/Sprinkle Road
- NB Sprinkle Road ramp to EB I-94
- NB Sprinkle Road ramp to WB I-94
- SB Sprinkle Road ramp to WB I-94
- Cork Street bridge over I-94
- Sprinkle Road lane closures between Cork Street and Midlink Drive. One lane will remain open in each direction.
The following lane closures apply to I-94 (weather dependent).
- Nightly lane closures and shoulder closures on EB and WB I-94